UPDATE: Stage 2 load shedding has been implemented at 9am
According to the power entity additional units were lost overnight.

Update at 9am:
Eskom has announced that Stage 2 load shedding will be taking place from 9am and is likely to continue until 10pm.
#PowerAlert 2 : Eskom implements Stage 2 rotational #loadshedding @CityPowerJhb @CityofJoburgZA @City_Ekurhuleni @CityofCT @CityTshwane @eThekwiniM @TrafficSA @ewnupdates @SABCNewsOnline pic.twitter.com/Emk5Lg61ZP
— Eskom Hld SOC Ltd (@Eskom_SA) November 30, 2018
Original article:
There is a high probability of stage load shedding from 9am to 10pm on Friday.
Eskom said it would only be implemented if absolutely necessary.
According to the power entity additional units were lost overnight.
Stage 2 calls for 2 000 MW to be rotationally shed nationally at any given period. Load shedding is conducted as a last resort to protect the power system from a total collapse or blackout.
Should load shedding be implemented on Friday, here are the times and suburbs for Tembisa and Olifantsfontein.
9am to 10.30am: Winnie Mandela Park Ext 4, Winnie Mandela Park Ext 1, Moriting, Mashimong, Kopanong, Makulong, Sethokga, Sedibeng, Hospital View/Gardens & Hill
10am to 1pm: Maokeng, Tlamatlama, Kopanong, Tsepo, Tsenelong, Temong, Leboeng, Ext 5, Winnie Mandela
12.30pm to 3.30pm: Winnie Mandela, Winnie Mandela Zones (Clayville), Clayville 13, Douglass, Clayville East
3pm to 6pm: Birch Acres from Ext 23 up to Ext 44, Jiyane, Isiphetweni, Ehlanzeni, Welomlambo, Vusimuzi, Isiziba, Ibaxa, Inxiweni, Emfilweni, Emkatini, Ibazelo, Igqagqa, Isithame, Isivana, Ethafeni, Endulweni, Esiziba
5.30pm to 8.30pm: Ext 5, Teanong, Seotloana, Motsu, Moteong, Lekaneng, Lifateng, Thiteng, Esangweni, Umthabeka, Umfuyaneni, Ext 11, Entshonalanga, Endayeni, Gahlantso, Umnonjaneni, Entshonalanga, Moedi, Kgatlamping
8pm to 10pm: Emangweni, Ext10, Illiliba, Emoyeni, Emfilhweni, Isiziba, Isekelo, Endulweni, Elindinga, Igqagqa, Isithame, Emoyeni, Mqantsa, Xubeni, Ecaleni, Ext 7, Ext 9, Ext 8