Here is you load shedding schedule for Tembisa for Sunday
Load shedding is expected to continue until 10pm

After two months without load shedding, Eskom has implemented stage 2 load shedding on Sunday at 1pm.
As previously, it is expected to last until 10pm. Load shedding was last implemented on December 9.
In a statement Eskom issued earlier today, the power utility said it had a shortage of capacity. There is also a need to replenish and preserve emergency water and diesel resources to limit load shedding possibility or the magnitude thereof in the coming week.
Stage 2 calls for 2000MW to be rotationally shed nationally at a given period. Load shedding is conducted rotationally as a measure of last resort to protect the power system from a total collapse or blackout.
“We continue to appeal to residents and businesses to use electricity sparingly during this period. Please switch off geysers as well as all non-essential lighting and electricity appliances to assist in reducing demand.
This is the schedule for Tembisa and Olifantsfontein:
12.30pm – 3.30pm: Ext 5, Teanong, Seotloana, Motsu, Moteong, Lekaneng, Lifateng, Thiteng, Esangweni, Umthabeka, Umfuyaneni, Ext 11, Entshonalanga, Endayeni, Gahlantso, Umnonjaneni, Entshonalanga, Moedi, Kgatlamping
3pm – 6pm: Emangweni, Ext10, Illiliba, Emoyeni, Emfilhweni, Isiziba, Isekelo, Endulweni, Elindinga, Igqagqa, Isithame, Emoyeni, Mqantsa, Xubeni, Ecaleni, Ext 7, Ext 9, Ext 8
5.30pm – 8.30pm: Winnie Mandela Park Ext 4, Winnie Mandela Park Ext 1, Moriting, Mashimong, Kopanong, Makulong, Sethokga, Sedibeng, Hospital View/Gardens & Hill
8pm – 10pm: Maokeng, Tlamatlama, Kopanong, Tsepo, Tsenelong, Temong, Leboeng, Ext 5, Winnie Mandela