Thembisa’s stage 2 load-shedding schedule for Tuesday
Stage 1 load shedding was only stopped at 5am on Tuesday morning.
A further delay in the return of generation units resulted in Eskom to increase load-shedding to stage 2 from 9am on Tuesday.
The power utility did not specify until when this would last but said rolling blackouts were likely to continue for the rest of the week.
Stage 1 load shedding was only stopped at 5am on Tuesday morning.
Tuesday’s schedule for Thembisa is:
9am – 10.30am: Winnie Mandela, Winnie Mandela Zones (Clayville), Clayville 13, Douglass, Clayville East
10am – 1pm: Birch Acres from Ext 23 upto Ext 44, Jiyane, Isiphetweni, Ehlanzeni, Welomlambo, Vusimuzi, Isiziba, Ibaxa, Inxiweni, Emfilweni, Emkatini, Ibazelo, Igqagqa, Isithame, Isivana, Ethafeni, Endulweni, Esiziba
12.30pm – 3.30pm: Ext 5, Teanong, Seotloana, Motsu, Moteong, Lekaneng, Lifateng, Thiteng, Esangweni, Umthabeka, Umfuyaneni, Ext 11, Entshonalanga, Endayeni, Gahlantso, Umnonjaneni, Entshonalanga, Moedi, Kgatlamping
3pm – 6pm: Emangweni, Ext10, Illiliba, Emoyeni, Emfilhweni, Isiziba, Isekelo, Endulweni, Elindinga, Igqagqa, Isithame, Emoyeni, Mqantsa, Xubeni, Ecaleni, Ext 7, Ext 9, Ext 8
5.30pm – 8.30pm: Winnie Mandela Park Ext 4, Winnie Mandela Park Ext 1, Moriting, Mashimong, Kopanong, Makulong, Sethokga, Sedibeng, Hospital View/Gardens & Hill
8pm – 11pm: Maokeng, Tlamatlama, Kopanong, Tsepo, Tsenelong, Temong, Leboeng, Ext 5, Winnie Mandela
10.30pm – midnight: Winnie Mandela, Winnie Mandela Zones (Clayville), Clayville 13, Douglass, Clayville East
Midnight – 3am: Ext 5, Teanong, Seotloana, Motsu, Moteong, Lekaneng, Lifateng, Thiteng, Esangweni, Umthabeka, Umfuyaneni, Ext 11, Entshonalanga, Endayeni, Gahlantso, Umnonjaneni, Entshonalanga, Moedi, Kgatlamping
2.30am – 5.30am: Emangweni, Ext10, Illiliba, Emoyeni, Emfilhweni, Isiziba, Isekelo, Endulweni, Elindinga, Igqagqa, Isithame, Emoyeni, Mqantsa, Xubeni, Ecaleni, Ext 7, Ext 9, Ext 8