Outstanding payments delay progress on Elgin Bridge project
At this stage, a confirmed installation date and overall completion date have yet to be provided by the relevant municipal departments.
Outstanding payments to the contractor have reportedly affected progress on the Elgin Bridge project in Kempton Park, while the procurement process for new gantries has commenced.
Ward 15 councillor Amanda Davison shared an update on November 26, acknowledging residents’ frustration over the long-running infrastructure challenge, with concerns about the bridge dating back to the 1970s.
According to Davison, feedback she received from municipal officials indicates that outstanding payments to the contractor have affected the pace of work, with the contractor indicating that payments are needed to accelerate progress on site.
Also read: Ward councilor and CoE comment on Elgin bridge
The procurement process for the new gantries required for the bridge has, however, commenced.
What needs to happen next?
Davison outlined several outstanding steps before the project can progress towards completion.
The City must first address and finalise outstanding payments to the contractor to allow work to progress. The procurement process for the new gantries must then be completed, followed by their manufacturing and delivery to site.
Once the gantries arrive, installation can proceed in accordance with the approved engineering and construction programme.
The remaining construction work and safety requirements must also be completed before the project can be signed off and the bridge fully reopened, where applicable.
“At this stage, a confirmed installation date and overall completion date have yet to be provided by the relevant municipal departments.”
Davison said she would continue following up with the departments to obtain these timelines rather than provide residents with dates that have not been officially confirmed.
Also read: CoE responds to the Elgin Bridge issue
Budget allocations
According to the councillor’s update, the City has made the following budget allocations for the project:
- 2024/2025: R300 000, with no expenditure recorded.
- 2025/2026: R500 000.
- 2026/2027: R500 000.
Davison said she would continue engaging with the relevant departments to monitor progress, obtain updates and keep residents informed.