Stage 2 load-shedding implemented by Eskom
RANDBURG – Power utility, Eskom announced stage 2 load-shedding yesterday. Stage 2 will be implemented today again.

According to a statement released by Eskom, during Stage 2 load shedding, 2000 megawatts will be shed nationally at a specific time that is set by Eskom.
This load-shedding is necessary due to a shortage of capacity. Customers are therefore reminded that the electrical points are live during load-shedding.
The load will be shed from 8am and last until 11pm.
Loadshedding stage 2 will be implemented from 08h00 to 23h00 today due to a shortage of capacity.@CityPowerJhb @City_Ekurhuleni @CityofCT @CityofJoburgZA @eThekwiniM @CityTshwane @TrafficSA @ewnreporter @SABCNewsOnline @IOL
— Eskom Hld SOC Ltd (@Eskom_SA) March 15, 2019
These are some of the affected areas in Randburg:
8A NORTHRIDING.^LP pic.twitter.com/iDWb5h7lHp
— @CityPowerJhb (@CityPowerJhb) March 15, 2019
You can check which area you fall under by looking at the below information,
ALERT:#Load-shedding: Eskom has declared stage 2 rotational load-shedding from 08h00 until 23h00. Please check which block your area belongs to on the attached updated list of blocks.^LP pic.twitter.com/YjCGbnrcKz
— @CityPowerJhb (@CityPowerJhb) March 15, 2019
UPDATE:#Load-shedding: Eskom stage 2 rotational load-shedding continues from 16h00. Block 4A and 8A are affected.^LP pic.twitter.com/c43DEbKEfa
— @CityPowerJhb (@CityPowerJhb) March 14, 2019
UPDATE: #Load shedding: City Power has received declaration of stage 2 load shedding from Eskom. Blocks to be affected are mentioned below.^JM pic.twitter.com/cu462zYfS4
— @CityPowerJhb (@CityPowerJhb) March 15, 2019
Related article: