Construction of Wessel Street in Ermelo expected to be completed in due course

According to Mr Mandla Zwane, spokesman for Msukaligwa Local Municipality, the project began late last year however, the physical onsite work began in March 2021.

ERMELO – The upgrading of the road and storm water drainage system of Wessel Street is expected to be completed by the end of August.

According to Mr Mandla Zwane, spokesman for Msukaligwa Local Municipality, the project began late last year however, the physical onsite work began in March 2021.

“The municipality appointed Tirisano Consulting Engineers who in return appointed a contractor,” he said.

“The project is funded by the municipality.”

The construction phases consist of:

• Site preparation

• Subgrade

• Stabilisation

• Base

• Kerbing and channeling

• Prime and asphalt surfacing

• Permanent traffic sign installation

• Storm water drainage

Mr Zwane concluded that contracters are currently busy with the prime and asphalt surfacing phase.

At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Ridge Times in Google News and Top Stories.

Wayne van der Walt

Wayne van der Walt, with around 15 years in the media industry, is editor of Highvelder Newspaper. His accolades include Frewin Awards for Newspaper of the Year and Front Page of the Year, and FCJ Photographer of the Year, among other honours.

Related Articles

Back to top button