NewsNews

R115 million wasted on incomplete wards at Kopanong hospital

A hospital wing of about 300 beds would be built behind the existing hospital to increase capacity.

VEREENIGING. – R115 million was spent at the Kopanong hospital in Vereeniging on wards meant to be used for the Covid-19 pandemic.

This was revealed in a statement by the Democratic Alliance (DA) Gauteng Shadow Health Spokesperson Jack Bloom, stating that not a single ward has been completed to date.

According to Bloom, the details were revealed by the Gauteng Health MEC Nomantu Nkomo-Ralehoko in a written reply to his questions in the Gauteng Legislature.

According to the MEC, the wards are all incomplete because the appointed service provider was unable to finish the project and the contract was terminated.

The original plan in 2020 was to rapidly build 300 ICU beds for Covid-19 patients using Alternative Building Technology (ABT), but fell way behind schedule and was never used.

During his visit to the hospital, former Health MEC Doctor Bandile Masuku said that the Gauteng Department of Health had undertaken the huge task of increasing capacity in hospitals in order to meet the pressures of the COVID-19 pandemic.

A hospital wing of about 300 beds would be built behind the existing hospital to increase capacity. Masuku said the project is an essential stepping stone to improving the state of health in Vereeniging and surrounding areas.

“There was also controversy because the contractor failed to pay subcontractors. Now the Department says they are “reviewing the structure for possible use as office space for the district.”
According to Bloom, the project has been a huge waste of money that should have been used to fix existing public hospitals.

“It’s yet another example of gross incompetence by the Gauteng Department of Infrastructure Development (GDID) which routinely chooses poor contractors who fail to finish but still get paid huge amounts of money. As usual, corruption is suspected and the MEC says GDID is investigating the issue.”

The DA says it is yet to see any real consequences from the never-ending “investigations”. Bloom says a complete management shake-up is needed to clear up the rot.

“This will never happen under the ANC as they provide political protection to corrupt and incompetent people.”

At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Sedibeng Ster in Google News and Top Stories.

Lebohang Chaha

Lebo Chaha is a journalist for Sedibeng Ster and Ster North. She is mostly passionate about stories that bring positive change in her community. Email: lebo@mooivaal.co.za

Related Articles

Back to top button