Load shedding schedule for Thursday, October 28:
Ga-Nala and KwaGuqa Substation will be affected from 09:00 until 11:30.
Grobler Substation will be affected from 11:00 until 13:30.
Buffer Substation will be affected from 13:00 until 15:30.
Clewer, Ogies, Phola, Doornpoort, Rietspruit and KwaGuqa Substation will be affected from 15:00 until 17:30.
Ga-Nala and KwaGuqa Substation will be affected from 17:00 until 19:30
Grobler Substation will be affected from 19:00 until 21:30.
Buffer Substation will be affected from 21:00 until 23:30.
Clewer, Ogies, Phola, Doornpoort, Rietspruit and KwaGuqa Substation will be affected from 23:00 until 01:30.
Friday, October 29:
Buffer Substation will be affected from 03:00 until 05:30.
Clewer, Ogies, Phola, Doornpoort, Rietspruit and KwaGuqa Substation will be affected from 05:00 until 07:30
Ga-Nala and KwaGuqa Substation will be affected from 07:00 until 09:30.