Johannesburg Roads Agency clarifies Ward 115 road maintenance constraints

Agency disputes claims of widespread road maintenance funding constraints but confirms reduced funding for major infrastructure projects.

Concerns raised by Ward 115 councillor Mark van der Merwe about budget and procurement constraints affecting road maintenance have prompted the Johannesburg Roads Agency (JRA) to clarify its position on service delivery.

Van der Merwe raised concerns about several road infrastructure challenges in Ward 115, arguing that financial constraints across the City of Johannesburg were making it increasingly difficult for municipal entities to carry out maintenance and upgrades.

Among the issues he highlighted were potholes, road markings, Platina Bridge repairs, Randa Road resurfacing and stormwater infrastructure on Juweel and Randa roads.

Read more: JRA begins removing Lombardy Road rubble

Van der Merwe also said repairs on Platina Street had been affected by the closure of the city’s asphalt plant, claiming that there was no cold tar available for temporary repairs.

However, JRA head of department for infrastructure development Kwazelela Mcetywa said routine road maintenance in Ward 115 is not currently affected by regional budget constraints, while acknowledging that reduced funding has affected major infrastructure projects.

The state of the roads in parts of Ward 115. Photo: Ayanda Ntshingila

Mcetywa said regional operations are funded through an operational expenditure budget covering all wards in a region and that Region E is not experiencing budget constraints affecting routine road maintenance.

He confirmed a disruption to repairs on Platina Street after its asphalt plant experienced operational problems.

Also read: JRA admits rubble is theirs contractor stored

“Repairs on Platina Street began on the same day the asphalt plant broke down, meaning the work could not proceed. As soon as the plant is producing, all areas that were prepared for repairs will be attended to.”

On road markings, Mcetywa said paint has been procured, and the agency is waiting for delivery, after which level 1 maintenance will proceed.

The agency’s response also reveals a distinction between routine maintenance and larger capital-intensive projects.

“Regarding Platina Bridge and Randa Road resurfacing, the JRA has been adversely impacted by limited budget allocation in the current financial year, where a reduced budget for bridges and resurfacing programmes was allocated. The JRA will request budget from the City at the mid-term budget adjustment period to proceed with the implementation of Platina Bridge and resurfacing.”

Follow us on our Whatsapp channelFacebookXInstagram and TikTok for the latest updates!

At Caxton, every story is written by humans. We use AI only to perform quality checks - never to generate the news. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Fourways Review in Google News and Top Stories.

Ayanda Ntshingila

Ayanda Ntshingila is an aspiring intern journalist at Caxton Local Media, skilled in news writing and reporting with a passion for storytelling. She is currently contributing to Fourways Review.

Related Articles

Back to top button