Many Kemptonians should prepare themselves for at least another two to three days without electricity.
According to a post on the City of Ekurhuleni website on Saturday evening the prospects are bleak to restore power to those areas affected since Friday morning.
According to the post posted at around 8.30pm on Saturday evening, the City was not able to give an estimated restoration time due to the complexity of the repair work.
Also read:
• “Tunnel fire” could have caused major power outage in Kempton
• More areas plunged into darkness this morning
Technicians are restoring customers through temporary connections while repairs are on going. pic.twitter.com/rAlkYTvBeT
— CITY OF EKURHULENI (@City_Ekurhuleni) September 21, 2019
The damaged cables are 66kV oil-filled cables. Once the cables have been repaired the oil has to be drained, tested and purified to be within specifications before it could be energised. The whole process, including the testing phase, could take until Tuesday, or longer, the metro said.
“We are restoring customers through temporary connections while repairs are on-going, the metro said.
The damaged cables are 66kV oil filled. Once the cables have been repaired the oil is drained, tested, and purified to be within specification before it can be energized. The whole process, including testing phase, could take until Tuesday, or longer.
— CITY OF EKURHULENI (@City_Ekurhuleni) September 21, 2019