City of Ekurhuleni begins repairs to collapsed Terenure stormwater drain
City of Ekurhuleni is starting with the stormwater pipe project repairs after causing a wall at a residential complex.
After almost a year of uncertainty, work is finally underway to repair the collapsed stormwater drainage system that damaged a Terenure property and left a resident fearing for her family’s safety.
According to Ward 104 Clr Tracey Lourenco, a contractor was officially appointed on June 17 to repair and reconstruct the collapsed stormwater infrastructure.
“Before construction can begin, several contractual requirements must be completed, including health and safety compliance, site establishment, and the mobilisation of equipment and materials,” said Lourenco.
ALSO READ: Stormwater chaos in Kempton Park: Residents demand urgent municipal action
She recently met with City of Ekurhuleni officials and the appointed contractor on site to discuss the way forward.
“The contractor will rebuild the existing stormwater system and reinstate the affected resident’s boundary wall, while also repairing damage caused to the property.”
Lourenco said the first phase of the project is expected to take about two months to complete.
The second phase will begin once the necessary funding has been approved. This phase will extend the upgraded stormwater system alongside the complex, improving the flow of stormwater away from the boundary wall to reduce the risk of future flooding and provide a more sustainable long-term solution.
“This project marks an important step in addressing a longstanding issue, and I will continue to monitor progress to ensure the work is completed as efficiently and effectively as possible. I welcome this contract because it will greatly improve the lives of the residents affected by the stormwater collapse,” she said.
ALSO READ: Apply for the City of Ekurhuleni’s Indigent Support Programme
The Kempton Express first reported on the matter in its December 11, 2025, edition after Condere Estate resident Winnie Mojela’s worst fears materialised when part of her boundary wall collapsed due to an unfinished stormwater pipe project behind her property.
The problem was first reported on January 30, 2025, when Mojela noticed flooding in her yard and a large trench forming outside her boundary wall.
The collapse left her property vulnerable and raised concerns about the safety of her family.
Mojela said she appreciated the progress made so far but remained cautiously optimistic while the work continued.
“I am grateful to see the progress. Although it is still early to comment because the project has just started, I appreciate the work and effort the City of Ekurhuleni has made.
ALSO READ: City of Ekurhuleni hands over 140 houses to Thembisa beneficiaries in Clayville
“It is a great relief for my family and me to see the progress. At this stage, the new stormwater pipe has not yet been installed, but I can confirm that the water has been diverted away from our wall and work is continuing where the problem occurred.
“I strongly believe they will carry out the repairs properly as I monitor the progress every day. So far, I am impressed.”
Mojela said the incident had significantly affected her family and believes the damage could have been prevented had earlier reports to the City been addressed.
She also thanked the body corporate of the complex for arranging temporary security while a replacement fence is erected.
“It was not safe because the area behind our property is secluded and overgrown, creating places where suspects could hide. I also had to spend money on additional security upgrades because I felt my family and I were exposed.”
She also thanked the Kempton Express for highlighting her concerns.