Mayibuye road upgrades on hold as JRA prepares contractor replacement
JRA confirms it has terminated the previous contractor's agreement and is preparing to procure a replacement after construction stalled at 25%.
The Johannesburg Roads Agency (JRA) is moving towards appointing a replacement contractor to complete the stalled R15m Mayibuye road rehabilitation project, eight months after construction began.
After the article, Sinamurula Street still unusable, [Week ending: November 13, 2026], the agency confirmed that it terminated its agreement with the appointed contractor in September after due contractual processes, when the project fell behind schedule and reached only 25% completion.
Read more: Midrand councillors call out JRA over unfinished projects
The development comes after concerns raised by Mayibuye community leader Tapelo Nkoane, who called on the agency to intervene and appoint a new contractor to complete the outstanding work.
JRA head of infrastructure development Kwazelela Mcetywa said the agency was finalising the necessary contractual and administrative processes to pave the way for a replacement contractor.

“The project commenced on March 23 [this year]; however, the contract with the contractor was terminated in September following due contractual process. The JRA is closing out the project to commence with the procurement of a replacement contractor to complete the works,” said Mcetywa.
He confirmed that construction had reached only 25% at the time of termination, adding that there were currently no construction activities on site. Despite the setback, Mcetywa said the project remained a priority for the agency, particularly because of its implications for residents’ safety.
Also read: 4 billion litres of sewage spews into water system daily
The project, which has an allocated budget of R15m for the 2026/27 financial year, aims to upgrade about 1.185km of roads in Mayibuye by converting existing gravel roads into tarred roads.
According to Mcetywa, the planned improvements include underground concrete stormwater pipes, kerb inlets and stormwater manholes to improve drainage and address water ponding and flooding.
The scope also includes milling the existing asphalt layer along Sinamurula and Bulelwa Makomane streets, installing mountable kerbs, constructing block-paved sidewalks, erecting road signs and installing speed humps.
Other works involve road layer construction and asphalt surfacing, with the overall aim of improving road geometry, traffic flow and safety for motorists and pedestrians.

The agency also anticipated that the project would contribute towards local economic development through employment and subcontracting opportunities.
Mcetywa confirmed that 16 employment opportunities had been created before the contract was terminated, against a target of 45 local labourers. Four of the nine SMMEs earmarked for civil works subcontracting had also been appointed.
With the previous contract terminated, the completion of the remaining work now depends on the appointment of a replacement contractor.
The JRA has, however, not provided a confirmed date for the procurement process to be completed or when construction is expected to resume.