Residents fear unfinished Klipfontein Wellness Centre could become another white elephant
The JDA has confirmed that construction of the Klipfontein Wellness Centre remains suspended because of budgetary constraints, with no revised completion date.
Elderly residents and families are still relying on healthcare facilities in neighbouring communities while waiting for a long-promised wellness centre in Klipfontein View to be completed.
For residents who had hoped to access healthcare services closer to home, the unfinished Klipfontein Wellness Centre represents another delay in getting a service they have campaigned for over more than 25 years.
Read more: Ivory Park residents demand answers as pool stands locked
Instead of welcoming patients, the facility remains incomplete, with construction suspended at approximately 60%, leaving residents uncertain about when they will finally benefit from the project.
Klipfontein View resident Masego Ntsie said the absence of a permanent healthcare facility continued to place pressure on residents, particularly elderly people who had to travel to Mayibuye, Rabie Ridge and Midrand to access medical services.
Although a mobile clinic operates in the area from Monday to Friday, Ntsie said its services were limited and could not cater for every healthcare need. “If I get injured and break my bone now, the mobile clinic will not be able to service me. It is either we must call an ambulance, but even that ambulance here in Klipfontein takes hours to get here,” she claimed.

Ntsie said residents were excited when construction began because they believed they would finally have access to healthcare services within their community.
Also read: Flies invade Rabie Ridge homes as residents demand closure of dumping site
“We have been waiting for this clinic as the community of Klipfontein for more than 25 years. When we saw it starting, as residents, we were excited. Honestly, we were happy that finally we were going to have access to health services just around the corner.”
The project was initially expected to be completed in April 2022, following an anticipated 18-month construction period, but delays and a subsequent procurement process pushed the development further behind schedule, with the Johannesburg Development Agency (JDA) officially breaking ground again in January 2024.
According to an August 2026 procurement document, construction was halted at about 60% completion because of financial constraints affecting the City of Johannesburg.

In late August 2026, the JDA issued an Expression of Interest inviting private developers, consortia and funders to submit proposals for a mixed-use development and long-term lease arrangement to help fund and complete the project.
Once operational, the facility will comprise a 2 175m² clinic and a 2 247m² drug treatment centre, offering healthcare, counselling, substance abuse treatment, rehabilitation and aftercare services.
Ntsie, a former project steering committee member, also raised concerns about the project’s implementation, alleging that local small businesses and residents had not benefited sufficiently from employment and procurement opportunities.
Also read: City Power launches solar high-masts in Rabie Ridge
Community leader Tapelo Nkoane said residents should not remain silent while important infrastructure projects were left incomplete.
“We cannot have projects being turned into white elephants while we watch. Imagine a 24-hour clinic that was supposed to save our people being left in such conditions,” he said.
JDA spokesperson Kenneth Nxumalo confirmed that construction was suspended because of budgetary constraints during the 2025/26 financial year. He said substantial progress had been made on the main building and associated infrastructure before the contractor left the site.

“The JDA is not yet able to confirm a revised practical completion date. The resumption of construction and a revised project programme depend on confirmation of the necessary funding allocations and the contractor’s subsequent return to site,” he said.
Nxumalo said the city and the JDA remained committed to completing the facility and were engaging with relevant stakeholders to address outstanding funding requirements.


In line with its mandate to deliver sustainable development, the JDA stated that it had employed labour-intensive methods for this project, providing vital short-term employment opportunities to unskilled and semi-skilled workers.

The agency said four subcontractors and 21 local small, medium, and micro enterprises were appointed, ensuring that the community benefits directly from the project, fosters economic
growth, and strengthens local involvement and the project’s success.