Joburg mayor announces R700m power boost for Honeydew and Ruimsig

City Power plans to resolve capacity issues and tackle ageing infrastructure with new bulk funding and a new substation opening by December.

Residents put long-standing frustrations over power faults, pending electricity approvals and dark streets directly to municipal leaders during a City Power electricity imbizo at Ruimsig Stadium on Thursday, September 3.

The public meeting brought together community members from wards 83, 85 and 97 to highlight prolonged power cuts, capacity constraints, non-functioning streetlights and individual supply faults.

City of Johannesburg Executive Mayor Dada Morero said the city had secured about R700m in additional capital funding for electricity infrastructure, on top of an existing budget of about R1.6b to R1.7b. Morero explained that the supplemental funds would allow the municipality to address capacity bottlenecks restricting local development and power supply.

City of Johannesburg MMC for Development Planning, Clr Eunice Mgcina. Photo: Neliswa Sibiya

Lutz Substation to ease capacity constraints

Acting City Power CEO Charles Tlouane told residents that load-related capacity issues were expected to be resolved by December when the Lutz Substation starts operating. Tlouane said that by December, the capacity issues should be resolved.

The Lutz Substation is an 88/11kV project constructed by City Power to boost bulk supply and relieve heavy pressure on the Peter Road and Kloofendal substations. It is set to reduce prolonged outages caused by overloading and cable theft affecting residents in Honeydew areas and some parts of Ward 97.

For some residents, however, the problems have been years in the making.

Ward 97 Clr Jacques Hoon shares a welcoming message to residents and City Power. Photo: Neliswa Sibiya

Long-standing property and supply delays

Louisa Sardinha from Ward 97, said her 89-year-old mother had been waiting for electricity approval for a property for 22 years, adding that the approval had been granted and withdrawn several times.

“All she wants is an approval of the electricity so that she can sell the property to a developer to develop,” she said.

Morero said City Power officials would take the family’s details and visit the property to determine the required intervention. Another Ward 97 resident, Lerato Takalo, said three businesses were relying on a 350kVA meter box that was struggling to cope with demand. She called for it to be upgraded to 500kVA or 700kVA. Morero said work to increase capacity was expected to start on Friday, September 11.

Another resident, Lerato Takalo, shares her concerns. Photo: Neliswa Sibiya

Streetlight backlog and infrastructure theft

Streetlights were another pressing issue. Resident Walter van Schalkwyk said he had been reporting faulty streetlights for more than two years.

“I personally have logged tickets for over two years. For two years, nothing has happened,” he said.

Tlouane said City Power would intensify work on the streetlight backlog and encouraged residents to continue reporting faults. He also said theft and vandalism remained a major cause of outages, accounting for 20% of City Power’s outages, and said the utility was replacing some copper infrastructure with aluminium.

Residents also raised concerns about a recurring Cypress Road electricity fault, which Angie Pipi said had resulted in phase-downs and damaged appliances.

The hall is packed with residents and City Power representatives. Photo: Neliswa Sibiya

Direct engagement on community concerns

The meeting was streamed live, while mobile offices at the stadium allowed residents to raise billing and electricity-related queries directly with officials. Questions submitted online included an update on new prepaid meters and concerns about recurring outages in Honeydew, which were addressed by the mayor. Morero said the city was also working to address ageing electricity infrastructure and attract further investment to strengthen bulk infrastructure in the area.

At Caxton, every story is written by humans. We use AI only to perform quality checks - never to generate the news. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Roodepoort Record in Google News and Top Stories.

Neliswa Sibiya

Neliswa Sibiya, a journalist for the Roodepoort Northsider, covers local news, human interest stories, municipal issues, sport, crime and community events. She holds an Advanced Diploma in Journalism from the Tshwane University of Technology. Her work focuses on giving the community a voice, and she enjoys meeting people, hearing their stories and shedding a light on issues that matter to the residents of Roodepoort.