Load shedding stage four from April 20 to April 22

Eskom will continue with Stage 4 load shedding until Friday, April 22 at 05:00.
The load shedding schedule is as follows:
April 20:
Ga-Nala and KwaGuqa Substation will be affected from 05:00 until 07:30.
Grobler Substation will be affected from 07:00 until 09:30.
Buffer Substation will be affected from 09:00 until 11:30.
Doornpoort, Rietspruit, KwaGuqa, Clewer, Ogies and Phola Substation will be affected from 11:00 until 13:30.
Ga-Nala and KwaGuqa Substation will be affected from 13:00 until 15:30.
Grobler Substation will be affected from 15:00 until 17:30.
Buffer Substation will be affected from 17:00 until 19:30.
Doornpoort, Rietspruit, KwaGuqa, Clewer, Ogies and Phola Substation will be affected from 19:00 until 21:30.
Ga-Nala and KwaGuqa Substation will be affected from 21:00 until 23:30.
Grobler Substation will be affected from 23:00 until 01:30.
April 21:
Doornpoort, Rietspruit, KwaGuqa, Clewer, Ogies and Phola Substation will be affected from 01:00 until 03:30.
Ga-Nala and KwaGuqa Substation will be affected from 03:00 until 05:30.
Grobler Substation will be affected from 05:00 until 07:30.
Buffer Substation will be affected from 07:00 until 09:30.
Doornpoort, Rietspruit, KwaGuqa, Clewer, Ogies and Phola Substation will be affected from 09:00 until 11:30.
Ga-Nala and KwaGuqa Substation will be affected from 11:00 until 13:30.
Grobler Substation will be affected from 13:00 until 15:30.
Buffer Substation will be affected from 15:00 until 17:30.
Doornpoort, Rietspruit, KwaGuqa, Clewer, Ogies and Phola Substation will be affected from 17:00 until 19:30.
Ga-Nala and KwaGuqa Substation will be affected from 19:00 until 21:30.
Grobler Substation will be affected from 21:00 until 23:30.
Buffer Substation will be affected from 23:00 until 01:30.