Repairs complete: Gradual power restoration underway in Ermelo

The municipality has apologised for the inconvenience caused.

UPDATE: 16:31 – January 9

Mandla Zwane announced that the repairs have been completed. The municipality will now begin restoring power section by section while monitoring the load.


Eskom arrives on-site to assist with electricity outage in Ermelo

January 9 – 15:31

Recent power disruptions have affected several areas in Ermelo due to a loose connection on the 88kV overhead feeder line.

The outages have impacted all areas connected to the 88kV substation, including Ermelo suburbs, the CBD, and Ext 32 to 34.

According to Mandla Zwane, Msukaligwa Local Municipality’s spokesperson, technicians from Eskom were alerted and have now arrived on-site to address the fault.

The municipality apologised for the inconvenience caused and assures residents that efforts are underway to restore electricity as quickly as possible.

Residents are encouraged to treat all electricity as live during this time.

At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Highvelder News in Google News and Top Stories.

Wayne van der Walt

Wayne van der Walt, with around 15 years in the media industry, is editor of Highvelder Newspaper. His accolades include Frewin Awards for Newspaper of the Year and Front Page of the Year, and FCJ Photographer of the Year, among other honours.

Related Articles

Back to top button