Mogale City insists new civic centre ready despite unpaid contractor claims
A local councillor alleges work stalled over unpaid service providers, but municipal officials say only a final snag list remains.
Mogale City Local Municipality insists that its recently unveiled civic centre is ready for use despite claims by a local councillor of incomplete works and unpaid contractors.
After the unveiling of the Mogale City Civic Centre on October 23, Ward 20 councillor Mark Trump publicly alleged that the municipality has not paid contractors on the project, disrupting construction progress.
• Read the initial article here: Row erupts over Mogale Civic Centre launch amid claims building is unfinished
After the allegation, Adrian Amod, the municipality’s head of corporate communications, confirmed that the municipality is not aware of any disruption to construction progress caused by non-payment to the service provider.
“While payments are linked to the achievement of specified milestones and the completion of work in accordance with the contractual requirements, there is a project snag list being worked on. Full payment will thus only be made with said pending work completed,” Amod said.
Municipality addresses occupancy status
The municipality confirmed that the building has not yet been occupied by its intended users, adding that while the occupancy certificate is expected to be issued within a few weeks, no date or total costs have been confirmed.