Stage 6 load-shedding implemented until further notice
Eskom says stage 6 load-shedding is likely to be implemented throughout the week.

Stage 6 load-shedding has been implemented from 16:00 today until further notice.
Eskom said in a media statement that load-shedding has been increased due to the failure of several generating units, and a delay in returning generating units to service.
“This is anticipated to persist throughout the week. Eskom will publish a further update as soon as any significant changes occur.”
According to the power utility, breakdowns currently stand at 19 333MW of generating capacity, while generating capacity that is unavailable due to planned maintenance stands at 4 524MW.
Stage 6 loadshedding will be implemented from 16:00 this afternoon until further notice pic.twitter.com/LPYw7tNUu2
— Eskom Hld SOC Ltd (@Eskom_SA) May 7, 2023