Some 20 000MW of capacity out of play as Eskom brings back stage 2 loadshedding

Loadshedding is set to start at midday today - January 14 - and continue until 11pm on Sunday, January 17.

Coal conveyor belts have failed at Kusile Power Station, tripping two generation units which have forced Eskom to hand out a dose of stage 2 loadshedding.

Loadshedding is set to start at midday today – January 14 – and continue until 11pm on Sunday, January 17.

Units at the Kriel and Duvha power stations have further tripped owing to the breaking down.

“We currently have four generation units which return to service from planned maintenance has been delayed.”

A total of 20 106MW of capacity is unavailable.

Eskom has assured the public that it is working tirelessly to return units to service.

Meanwhile, this is how stage 2 loadshedding is set to affect you:

Thursday:

Stanger Northern Grid: 2pm to 4.30pm, and again at 10pm to 00.30am.

Ballito Southern Grid: 10pm to 00.30am.

Tongaat CBD: No loadshedding.

Tongaat Beach: No loadshedding.

Mandini: No loadshedding.

Mandini A: No loadshedding.

Mandini B: Midday until 2.30pm.


Stay in the loop with The North Coast Courier on FacebookXInstagram & YouTube for the latest news.

Mobile users can join our WhatsApp Broadcast Service here, or if you’re on desktop, scan the QR code below.

At Caxton, every story is written by humans. We use AI only to perform quality checks - never to generate the news. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from North Coast Courier in Google News and Top Stories.

Back to top button