Councillors demand clarity Johannesburg Water payment dispute raise concerns over project delays

Councillors Marilyn Smouse and Kyle Jacobs are calling on Johannesburg Water for answers after Mapitsi Civil Works contractors downed tools in protest over non-payment on the Hursthill 2 reservoir rehabilitation works.

Ward 82 councillor Marilyn Smouse says residents are becoming increasingly frustrated over uncertainty surrounding the Hursthill 2 reservoir (HH2) project, following a payment dispute that prompted workers linked to contractor Mapitsi Civil Works to protest outside Johannesburg Water’s (JW) offices on August 7.

Smouse said the issue extends beyond the contractor dispute, with many residents already experiencing ongoing water interruptions and low pressure. “The reaction from residents has been one of frustration, disappointment, and growing concern. Residents are tired of ongoing water challenges and want to see tangible progress on infrastructure that is critical to securing a reliable water supply.”

Read more: Johannesburg Water payment delays halt Hursthill reservoir project, leaving residents fuming

Lesang Diradingwe: Since having not been paid for three months, I do not have money to pay for my children’s transport for school. This has affected me overall as a provider for my family. Photo: Waydon Jacobs

She described HH2 as a critical part of the wider Commando water system, saying it directly affects households, schools, businesses, and vulnerable residents across Ward 82 and neighbouring communities. Smouse said residents do not want contractual disputes to delay a project that is urgently needed, and called on JW to improve communication with affected communities. “JW should provide regular updates explaining where the project stands, what work has been completed, what challenges have arisen, whether the completion date has changed, and what contingency measures are in place.”

Protesters display placards as contractors demand payment after alleging they have gone unpaid for more than three months. Photo: Waydon Jacobs

Ward 87 councillor Kyle Jacobs said the payment dispute reflects a broader pattern of delayed contractor payments affecting major infrastructure projects across Johannesburg. Jacobs said he had seen similar problems during construction of the Brixton reservoir and water tower, where work stopped repeatedly because contractors were not paid on time. “This is nothing new. We’ve seen this time and time again.”

Lerise Billings: The non-payment has left many of us unable to pay rent, school fees, or other essential expenses. Many employees have fallen into debt, while others have struggled to afford transportation to get to work. Photo: Waydon Jacobs

Also read: Hursthill 2 reservoir completion delayed until 2027 as contractor payment issues persist

He said contractors often keep projects running by using their own money to pay workers before eventually reaching a point where work can no longer continue. “The contractor does try and push a couple of months, and has to take money out of his own pocket to sustain operations and pay the staff, but the situation is untenable.”

Latimore Williams: Going three months without pay has torn my family apart. I cannot afford my children’s transport or meet basic household expenses. Photo: Waydon Jacobs

According to Jacobs, delayed payments affect more than construction schedules. “This has a direct impact, not only on the workers who are not getting paid, but also the residents who are going without water.”

Mapitsi Civil Works contractors chant outside Johannesburg Water head offices over non-payment on Hursthill 2 reservoir. Photo: Waydon Jacobs

He said the Brixton reservoir recently stood empty because insufficient water was reaching it from Rand Water and argued that, had HH2 been completed on schedule, it could have provided reserve capacity during recent maintenance. “It was supposed to be completed in April this year. If it had been done and the contractors had been paid when they were supposed to be paid, residents wouldn’t have felt the impact of the Rand Water maintenance to the extent they have.”

Ward 87 councillor Kyle Jacobs. Photo: Waydon Jacobs.

Jacobs criticised what he described as the city’s failure to prioritise essential infrastructure spending. “They’re not putting money where it matters most. It’s unacceptable and we can’t tolerate it.”

Mapitsi Civil Works contractors protest at Johannesburg Water head offices. Photo: Waydon Jacobs

Both councillors agreed that resolving the payment dispute quickly is essential to keeping the Hursthill 2 reservoir project on track and improving long-term water security for surrounding communities.

Follow us on our Whatsapp channelFacebookXInstagram, and TikTok for the latest updates!

At Caxton, every story is written by humans. We use AI only to perform quality checks - never to generate the news. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Northcliff Melville Times in Google News and Top Stories.

Related Articles

Back to top button