MunicipalNews

UPDATE: Metro says roadworks on Pretoria Road complete

As previously reported by the City Times, construction work began on Pretoria Road in February 2017.

The construction on Pretoria Road due to roadworks is complete, this according to Ekurhuleni metro spokesperson Themba Gadebe.

“The work at Pretoria Road (phase four of the 2018/19 financial year) is completed,” said Gadebe.

As previously reported by the City Times, construction work began on Pretoria Road in February 2017.

Numerous delays, which also affected businesses, primarily owing to a misunderstanding between the contractor and the sub-contractor, which resulted in work halted, were cited as reasons for the delays.

PREVIOUS READ: 

Pretoria Road roadworks bad for business

Business owners in the area also told the City Times that they expected the roadworks to take between five to six months to complete as per a letter they received.

This was, however, not the case as the roadworks were prolonged for over two years.

“The newly-constructed lanes were open for traffic on August 2 and the road markings and signs were completed on August 16,” concluded Gadebe.

 

 

At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Benoni City Times in Google News and Top Stories.

Related Articles

Back to top button