Stage 2 load shedding to continue until Monday

Here is your schedule

Despite promises that no load shedding would be implemented before January 13, Eskom will continue with stage 2 load shedding on Sunday from 8am until Monday at 5am.

The entity implemented stage 2 load shedding at 10pm on Saturday evening.

According to Eskom, the system remains constrained and vulnerable. The conveyer belt at Medupi Power Station has been repaired and the plant is feeding power into the grid.

This incident, however, as well as the loss of additional generation units, resulted in the depletion of diesel and pump storage levels, which need to be restored before the working week starts on Monday, Eskom said on Sunday morning.

The schedule for Kempton Park for Sunday until Monday morning:

7.30am to 10.30am: Geyser ripple control

10am to 1pm: Glen Marais, Allen Grove, Norkem Park, Birchleigh Extensions and Bonaero Park

12.30pm to 3.30pm: Birch Acres, Terenure, Edleen, Van Riebeeck Park, Kempton West

3pm to 6pm: Bredell, Pomona, Glen Marais Extensions (49, 52, 89 & 98), Serengeti, Brentwood Park, Aston Manor, Nimrod Park, Parts of Kempton Park Ext 2 & Ext 4

5.30pm to 8.30pm: Geyser ripple control

8pm to 11pm: Kempton Park CBD, Kempton Park Extensions, Croydon, Cresslawn, Rhodesfield, Kelvin Estate and Esther Park

10.30pm to midnight: Birchleigh, Birchleigh North, Glen Erasmia, Kaalfontein, Esselen Park and Esselen Park Extensions

Midnight until 3am: Birch Acres, Terenure, Edleen, Van Riebeeck Park, Kempton West

2.30qam to 5am: Bredell, Pomona, Glen Marais Extensions (49, 52, 89 & 98), Serengeti, Brentwood Park, Aston Manor, Nimrod Park, Parts of Kempton Park Ext 2 & Ext 4

 

At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Kempton Express in Google News and Top Stories.

Back to top button