Despite an earlier denial from the power utility, site registers and residents point to major pylon work stretching from Duvha Power Station towards Keerom.

Pylons are arising with planning documents, site accounts, and residents linking the power line construction to Eskom, despite the utility’s earlier denial
The question on many lips is; “Why has Eskom previously denied involvement and not yet replied to follow-up enquiries about the power line being constructed from the south of Middelburg towards Limpopo?”

Enquiries were sent to Eskom’s media desk on August 9

The straightforward question was: “There have been several cleared areas with cement blocks from Duvha Power Station all along the Duvha road to near Middelburg recently noticed by our readers who have enquired about them. According to a source, this is preparation for power cables that will be erected and is a network that will extend to Zimbabwe. Please provide more information because this is definitely an Eskom project. What is the planned electricity network for and the costs?”

On August 14, Eskom responded: “Please be advised that we are still working on your query and require more time. Therefore, we request an extension to Monday next week at 17:00.”

This commitment was not honoured.

On August 20, the Observer asked in its follow-up: “Please answer this simple question. It is not fair to give an undertaking that the information would be provided by Monday, yet it is now three days later. It is a simple question: Why are cement bases being constructed from Duvha through Middelburg? Is it for a power line to Zimbabwe?”

Eskom denies involvement after first report

After days passed without any response, an article was published regarding the pylons.

“Motorists along the Van Dyksdrift road have been left guessing as Eskom remains tight-lipped over major power line construction extending from Duvha Power Station. Land was cleared every few hundred metres before bases were built, with steel structures now lying in piles along the roadside.

“The steel piles extend from Duvha Power Station to Kruger Dam road, towards Aerorand.

“While the work appears to form part of an Eskom project, obtaining information from the media desk has proved unsuccessful.”

Only then did Eskom respond with: “Our sincere apologies for the delay in sending you the response. We also note that your article has been published, however, we request that the article be updated with the response below. Eskom can confirm that it does not have a project at Duvha Power Station or in the surrounding areas that corresponds with the activities described in your enquiry.”

After the Observer reported on the construction, more residents came forward, saying the pylons were also going to be erected on the section of land that previously belonged to Pienaardam owner Gerrie Gerrits, just beyond the Aerorand neighbourhood.

A day later, residents of the Keerom plots called and said that earthworks were being done in various places, indicating that the power line was extending to the north.

Scoping report outlines 400kV line plans

Later on, a draft scoping report that was sent to the Observer revealed that planning for the 80km Middelburg to Marble Hall power line began in 2007, despite Eskom denying involvement.

Nemai Consulting was appointed by Eskom in 2009 to undertake an environmental impact study, according to the draft scoping report.

“The document serves as the Draft Scoping Report for the proposed Emqiweni Substation and 400kV Line from Emqiweni Substation to Silimela,” the report states. “The proposed activity entails the construction of a 400kV power line from the Middelburg area in the south to the Marble Hall/Wolwekraal area in the north. The construction includes the Rockdale B Substation (now referred to as the Emqiweni Substation), with two 500MVA 400/132kV transformers; and the construction of the Rockdale B to Wolwekraal 400kV line (now referred to as the Emqiweni Substation to Silimela 400kV line).”

According to the report, Eskom decided to proceed with the construction of the approximately 80km Emchiweni-Silimela 400kV line, but the previous record of decision has lapsed.

“Therefore, Nemai Consulting is undertaking a new application for environmental authorisation as part of the 2014 EIA Regulations, as amended on April 7,” the report states.

Site register names contractor Siyavuya Power Projects

On Monday, an Observer journalist visited the construction site, where he was required to sign a visitor’s register that bore the name ‘Siyavuya Power Projects’.

A worker confirmed that he was employed by Siyavuya and that the contract was awarded to it by Eskom.

On November 15, further enquiries were sent to Eskom to ascertain whether the power utility still denies that this is an Eskom project, and whether Siyavuya was involved.

Eskom undertook to provide a response by 13:00 on November 17.

By November 19, the media desk had still not responded.

Enquiries were also directed to Siyavuya, and no reply had been received by publication.

A week has passed and no response has been received by publication to the November 15 follow-up enquiries regarding the scoping report and contractor.

WATCH VIDEO HERE:

Eskom still denies being involved in the construction of an 80km power… | TikTok

At Caxton, every story is written by humans. We use AI only to perform quality checks - never to generate the news. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Middelburg Observer in Google News and Top Stories.

Tobie van den Bergh

Tobie started as a journalist in September 1975. He was appointed editor of the Middelburg Observer in 1982 where he worked until he retired in 2024. He received numerous awards, is a founding member of the Forum for Community Newspapers and has published two books about his work. Although retired, Tobie is still very much involved in community journalism.
Back to top button