At this year’s Integrated Development Plan (IDP) presentation the electrification plan was discussed.
Mr Andre Beukes, Electrification Planner for Eskom, presented the electrification plan in the Msukaligwa area for 2019/20 year.
In the report, it stated that a total of 300 connections will be done in various areas in the Msukaligwa municipal area.
Areas such as Genesavat, Lothair portion 1, Vlakfontein, and Sheepstone portions, are four of several areas where connections will be made.
Over R8-mil will be spent on this project.
Read the complete article in the Highvelder newspaper.