News
Loadshedding – here’s the schedule for Middelburg
Stage two loadshedding continues for South Africa due to a severely constrained system.

According to a press release issued by Eskom, the company suffered breakdowns of ten generation units at seven power stations earlier this week.
Here is the loadshedding schedule for Middelburg and surrounds:
Wednesday 2 September
Middelburg / Mhluzi
None
Mall / Ext 18 / portion of Aerorand / Twizza
21h00 to 22h00
Nasaret / Rockdale / Ext24
None
Hendrina / Pullen’s Hope
8h00 to 9h30
15h00 to 17h30
Rondebosch / Keerom
15h00 to 17h30
Elandslaagte / Doornkop
9h00 to 11h30
17h00 to 19h30
Loskop
19h00 to 21h30
Arnot
13h00 to 15h30
21h00 to 22h00
Bethal
21h00 to 22h00
Ogies
19h00 to 21h30
Stoffberg
19h00 to 21h30