Load-shedding ramped up due to breakdowns
After a few days of lower stages of load-shedding, breakdowns have now led to stage 4 being implemented.

Eight generating units have broken down since last night, which has resulted in load-shedding being increased from this afternoon.
Eskom said in a short statement that stage 4 load-shedding will be implemented from 16:00 today until 05:00 tomorrow.
Thereafter, stage 3 load-shedding will be implemented between 05:00 and 16:00.
Eskom said a full media statement would be released later today.
#LoadsheddingUpdate
Wednesday, 19 July 2023:Due to the breakdowns of eight generating units since Tuesday evening, Stage 4 loadshedding will be implemented from 16:00 today until 05:00 on Thursday. Thereafter, Stage 3 loadshedding will be implemented from 05:00 until 16:00.…
— Eskom Hld SOC Ltd (@Eskom_SA) July 19, 2023