Umgeni interchange set for July completion

The M19/Umgeni interchange should be completed by the end of July, says SANRAL.

DURBAN motorists are breathing a sigh of relief following the opening of ramps A1 and A2 at the N2/M19 Umgeni interchange earlier this month.  The longest and highest ramp at the interchange was opened to motorists on 11 June and, prior to this, the south-bound and north-bound ramps leading onto the N2 at the same interchange were opened recently.

The interchange is scheduled for completion in July. But, according to the South African National Roads Agency SOC Ltd (SANRAL), this would largely depend on the contractor’s progress on the site.

SANRAL’s eastern region manager, Logashri Sewnarain, said: “Ramp A2 provides direct access for traffic from the N2 south heading towards Newlands/Inanda Road. In the original layout, the northbound traffic destined for Inanda/Newlands was required to take the Umgeni interchange off-ramp and then proceed across the signalised intersection on the M19 onto the service road and onto Inanda Road.”

At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Northglen News in Google News and Top Stories.

Shiraz Habbib

Shiraz has been a community journalist for the last 12 years and has a specific interest in everything sports. He holds a Bachelor of Arts undergrad degree and honours degree from the University of KwaZulu-Natal where he majored in Communications, Anthropology and English.