The JB Marks Local Municipality has issued a public notice informing residents of planned temporary electricity interruptions across Potchefstroom from Saturday, 9 May 2026 to Monday, 11 May 2026. The interruptions are part of scheduled maintenance and switching operations at various substations due to a transformer that needs to be repaired by Eskom.

The second transformer is expected to be back online by early next week. Once the repair is complete, stability will return and load curtailment will end.

Read the original story here:

According to the municipal spokesperson, Jeanette Tshite, different areas will be affected at different times during load reduction, with each outage lasting approximately 2 to 4.5 hours depending on the substation.

Saturday, May 9

  • 10:00 – 14:30: Promosa, Mohadin, Vuselela College area, Kenneth McArthur Stadium and CBD (Beta Substation)
  • 14:00 – 16:30: Ikageng Proper and extensions (Ikageng Main Substation)
  • 16:00 – 20:30: Industrial area, Suiddorp and Potchefstroom Hospital (Alpha Substation)
  • 20:00 – 22:30: Dassierand, Kanonierspark, The Bult, Steve Biko area, military base and Witrand (Gamma Substation)

Sunday, May 10

  • 06:00 – 10:30: Promosa, Mohadin and surrounding CBD areas (Beta Substation)
  • 10:00 – 14:30: Ikageng Proper and extensions (Ikageng Main Substation)
  • 14:00 – 16:30: Industrial area, Suiddorp and Potchefstroom Hospital (Alpha Substation)
  • 16:00 – 20:30: Dassierand, Kanonierspark, The Bult and surrounding areas (Gamma Substation)
  • 20:00 – 22:30: Miederpark, Grimbeekpark and CBD areas including municipal offices and malls (Epsilom and Delta Substations)

Monday, May 11

  • 06:00 – 10:30: Ikageng Proper and extensions (Ikageng Main Substation)
  • 10:00 – 14:30: Industrial area, Suiddorp and Potchefstroom Hospital (Alpha Substation)
  • 14:00 – 16:30: Dassierand, Kanonierspark, The Bult and surrounding areas (Gamma Substation)
  • 16:00 – 20:30: Miederpark, Grimbeekpark and CBD areas (Epsilom and Delta Substations)
  • 20:00 – 22:30: Promosa, Mohadin, Vuselela College area, Kenneth McArthur Stadium and CBD (Beta Substation)

At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Potchefstroom Herald in Google News and Top Stories.

wouterpienaar01

I am the editor of the Potchefstroom Herald since January 2026. I have a keen interest for sport and local community news. I have more than a decade of experience covering various beats. Journalism is a lifestyle.

Related Articles

Back to top button