Protests delay transformer delivery at Munic Substation

The municipality is pleading for patience from consumers in Miami Sands, CE 3 and 7 while technicians continue to work on efforts to restore power supply.

VANDERBIJLPARK.- The delivery of an electricity transformer that was set to land at Munic Substation on Monday, 12 July 2021 has been delayed.
Transformer concrete pad ramp construction.
The municipality jointly with the service provider hoped to move the 20 MVA transformer from Johannesburg to Vanderbijlpark on Monday however, due to violent protests currently plaguing Gauteng, most of the delivery routes have been closed.
Grading of the gravel road to access the substation has been completed, ready for the replacement transformer to arrive at Munic Substation soon as it is safe to do so.
The municipality is pleading for patience from consumers in Miami Sands, CE 3 and 7 while technicians continue to work on efforts to restore power supply. Updates will be communicated regularly as and when there are developments. We apologize for the inconvenience.
For more information contact the Electricity Control Room via WhatsApp on 065 871 7483.
At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Vaalweekblad in Google News and Top Stories.

Gugulethu Kgongoane

Gugulethu Kgongoane is the Online Editor of Sedibeng Ster. Email: gugu@mooivaal.co.za She is also an online journalist of Vaalweekblad. Email: gugu@mooivaal.co.za
Back to top button