Enos Mabuza to be done in two weeks

The upgrades to widen Dr Enos Mabuza Drive first started in January 2020.

The upgrades to Dr Enos Mabuza Drive will be finished within the next two weeks.  The upgrades to widen the road first started in January 2020 and were expected to be completed within 18 months.

ALSO READ: IN PHOTOS: Pumas fans champion their heroes

However, due to unforeseen delays, including the moving of two sensitive cables and lots of rain, the completion date was pushed back to June this year. White Hazy Construction’s Japie Visser said the project would be coming to an end in two weeks.

ALSO READ: Pangolin dies in White River

“We are busy with the last lane now. The rain caused some issues with the curing of the different layers of the road, but in two weeks, everything will be completed,” he said.

Do you have more information about the story?

Please send us an email to editorial@lowvelder.co.za.

For free breaking and community news, visit Lowvelder’s website: Lowvelder

For more news and interesting articles, like Lowvelder on Facebook, follow us on Twitter or Instagram

At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Support local journalism

Add The Citizen as a preferred source to see more from Lowvelder in Google News and Top Stories.

Back to top button